top of page

Marina Rebuild Timeline

Pelican Pulse
Sep 4
3 min read

Link to PDF version here, copied below.


PLCA Marina Rebuild History/Timeline Prepared by Ellen Dennis February 26, 2026 Presented at April 23,2026 PLCA Board Meeting


September 2022 –March 2023

September 28, 2022 – Hurricane Ian strikes

October 6, 2022 - March 16, 2023 – PLCA Board holds 20 meetings

March 23, 2023 – new Board seated


April 2023

Q. Grady Minor (QGM) meets with City of Bonita Springs (COBS) on marina zoning requirements

Board considers concept of good, better, best options for the marina rebuild


June 2023

Board discusses three potential marina rebuild options:

Option 1: Base option to replace existing facilities

Option 2: Add a 1000 sf covered observation deck

Option 3: Add a third floor for activities

Four architects interviewed with goal of developing site plan to take to COBS

Architects recommend getting a civil engineer on board first


July – October 2023

July – Board approves contract with Stantec to analyze marina property

August 1, 2023 - Board votes to terminate FirstService Residential contract. Staff begins work to return to self managed community

October 1, 2023 – PLCA again self-managed

October 20, 2023 – Beach re-opens (387 days after Ian)


November 2023

Stantec issues Boathouse Embarkation Feasibility study, using QGM work and contemplating 1,500 sf building with a finished floor elevation at approximately 16.33’ NAVD


January – March 2024

February 1, 2024 – Grace Lennon submits resignation; search for new GM begins

February - ORCO retained as owner’s representative for dock repairs, utilities and temporary fire connection

March 7, 2024 – Jim Hoppensteadt starts as COO/GM March – ORCO & PLCA staff meet with Bonita Springs Utilities on water / sewer calculations for new marina building

March 21, 2024 – new Board seated


April 2024

April – Ellen Dennis and Robert Haynes appointed marina rebuild liaisons to work with staff. Meeting with ORCO and architect Parker / Mudgett / Smith (PMS) to discuss objectives / options / obstacles.

Next steps will involve land use attorney, surveyor, and meeting with COBS. Architect needs parameters before starting work


May -June 2024

May – ORCO engaged for multiple projects, including marina building rebuild. Land use counsel and surveyor retained. Marina building and parking garage on wing lots concept introduced. Small facility still required near water which would be mobile.

June - ORCO provides cost estimates for various options; parking garage options are expensive


July - December 2024

July – Marina site survey completed. Options explored for mobile-only solution

August – Preliminary cost for connector driveway over $1mm. Further investigation on mobile solution / site utilization.

November – Pre-application meeting with COBS on mobile site plan. COBS and regulatory agencies take very restrictive view of site. Rebuild limited to square footage of old building. Driveway improvements and with water/sewer will be required. Mobile solution becomes increasingly attractive.


January – March 2025

February – Site plans and utility estimates for mobile option with quick disconnect trailers completed

March – Preapplication meeting with COBS on mobile concepts. COBS hard no to a permanent mobile solution. Back to rebuilding +/- 619 sf building with a finished floor elevation at approximately 16.33’ NAVD.

March 27, 2025 – New board seated


April - December 2025

April – With all parameters determined, architect PMS agrees to re-engage with objective of working with ORCO and PLCA to see what COBS could support.

May – Motion to approve proposal from PMS for conceptual design presented and withdrawn due to lack of support September – Motion to approve a proposal from PMS for conceptual design approved


January 2026

PMS provides preliminary floor plan and site location for a +/- 619 sf building with a finished floor elevation at approximately 16.33’ NAVD

Conversation between COO/GM and COBS development director on other matters leads to conversation about mobile option. Development director indicates he will listen to ideas

 
 

Recent Posts

See All
Bulk Internet/Cable Overview

Much information is circulating in the community regarding the Bulk Internet/Cable selection. Click this post to read more about it.

 
 
bottom of page